• Login
    Ver ítem 
    •   DSpace Principal
    • División Ingenierías
    • Departamento de Ingeniería Civil y Ambiental
    • Proyectos finales Pregrado en Ingeniería Civil y Ambiental
    • Ver ítem
    •   DSpace Principal
    • División Ingenierías
    • Departamento de Ingeniería Civil y Ambiental
    • Proyectos finales Pregrado en Ingeniería Civil y Ambiental
    • Ver ítem
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Centro Logístico en Fundación

    Transport Hub in Fundacion

    • Exportar citas
      • Exportar a Refworks
      • Exportar a Ris
      • Exportar a Endnote
      • Exportar a Mendeley
    URI
    http://hdl.handle.net/10584/8097
    Registro completo
    Mostrar el registro completo del ítem
    Autor
    López Nobmann, Andrés Felipe
    Marenco Barranco, Roy Enrique
    Orozco Arquez, Luz Angela
    Pérez Osorio, Andrés Felipe
    Zuluaga Rivas, Sebastián
    Fecha
    2018-06-11
    Resumen
    Actualmente en el municipio de Fundación se presenta una problemática con el transporte de pasajeros intermunicipales e interdepartamentales debido a que no cuenta con la infraestructura necesaria para movilizar los más de 150 viajes que se generan a diario. Esto se viene desarrollando informalmente en la entrada principal del municipio donde se encuentra ubicado el mercado, hecho que está generando un gran problema de congestión vial y sanitario. Considerando las altas tasas de viajes que se generan, se presenta como solución el diseño de un Centro Logístico a las afueras del casco urbano, buscando potenciar la economía. La propuesta se basa en el diseño de 3 estructuras. La primera será una edificación de un piso con 2643 m2 destinada para la Terminal de Pasajeros que contará con oficinas, locales y con 29 plazas de despacho y un sótano para el parqueo de los visitantes. La segunda será un hotel de 3 pisos de 661 m2 por nivel, albergando un total de 18 habitaciones para las personas que se encuentren de paso por el municipio y para que los conductores tengan un lugar disponible donde hospedarse sin necesidad de salir del complejo. Finalmente, la tercera comprenderá de 16 bodegas, destinadas para el almacenamiento de productos agrícolas que se producen en la región. El proyecto hace necesario la ampliación de la vía existente, por lo cual se plantea aumentar a una vía doble calzada con dos carriles por sentido y dos glorietas. Para cumplir con la visión sostenible del municipio, se complementará con un urbanismo destacado con vegetación propios de la zona. Durante el diseño, los estudios de suelos disponibles en la zona fueron limitados, además se deben tener en cuenta la intermitencia de fluido eléctrico e hidráulico, lo que hace que el proyecto deba tomar medidas para independizarse de la discontinuidad. Finalmente se logró obtener un proyecto cuya construcción tiene un valor de $14.492.006.062 y puede ser ejecutado en 18 meses.
     
    Nowadays, the municipality of Fundación undergoes several problems related to the inter-department and inter-municipality transportation of people and cargo, since it does not have the required infrastructure facilities to bear the more than 150 trips that are generated daily. Consequently, there exists an informal transport facility at the main entrance of the town, where the local market place is also located; this situation generates road congestion and several sanitary problems.Taking into account the high rates of generated travels, the design of a Transport Hub just outside the urban area of Fundación is proposed as a solution, seeking to boost its economy. The proposal is based on the design of three structures. The first one is a one-floor building of 2643 m2, intended to be the Passengers’ Terminal that will have offices, premises, 29 bus stop places, and a basement for the parking lot for visitors. The second one is a 3-floor hotel, planned to have an area of 661 m2 per floor and 18 rooms; it is envisioned to house passengers and bus and truck drivers, who would have an available place to stay without leaving the hub. Finally, the third one is constituted by 16 warehouses, intended for the storage of agricultural commodities that are produced in the region. This project makes necessary the enlargement of the existing road, for which it is proposed to increase to a dual-carriageway with two lanes in each direction and two roundabouts. To comply with the sustainable vision of the municipality, it will be complemented by an outstanding urbanism with vegetation typical of the area. During the design, the soil studies available in the area were limited. In addition, the intermittency of electric and hydraulic fluid must be taken into account, which means that the project must take measures to become independent of the discontinuity. Finally, it was possible to obtain a project which construction has a value of $14,492,006,062 and can be executed in 18 months.
     
    Colecciones a las que pertenece
    • Proyectos finales Pregrado en Ingeniería Civil y Ambiental [149]
    Vista Lateral del Centro Logístico en Fundación, Magdalena (163.3Kb)Visualizar
    -
    Vista de La Terminal de Transporte (2.698Mb)

    DSpace software copyright © 2002-2016  DuraSpace
    Contacto | Sugerencias
    Theme by 
    Atmire NV
     

     

    Listar

    Todo DSpaceComunidades & ColeccionesPor fecha de publicaciónAutoresTítulosMateriasEsta colecciónPor fecha de publicaciónAutoresTítulosMaterias

    Mi cuenta

    AccederRegistro

    DSpace software copyright © 2002-2016  DuraSpace
    Contacto | Sugerencias
    Theme by 
    Atmire NV